English > Business > Project general contracting > Municipal engineering > Shuangyong avenue and Tianyuan road intersection Pipeline migration project

Shuangyong avenue and Tianyuan road intersection Pipeline migration project

2024年10月09日     58人浏览

The project is located in Shuangyong avenue and Tianyuan road intersection, Jiangning district, Nanjing. It started in October 2018, completed in May 2019, including five road: Mapu street, Gaohu road, Zhuangpai road, Shuanglong avenue, and Tianyuan road, with a total length of 2300m. The main work includes pavement demolition, trench excavation, well inspection and construction, 28 + 10 holes weak electric pipeline laying and pavement construction. Shuanglong avenue was constructed by drag pipes, and the rest of the parts are using open construction.